===== Plan: ključni momenti ===== Plan aktivnosti u grupi za Fizičku infrastrukturu. Plan je predložen i usvojen u //subtask//-u A3 //task//-a NA3/T4. ^Code ^ Milestones ^ Date | |A3.1 |Working group in subtask A3 established with leader | October 2009 | |A3.2 |The initial draft of document “Requirements for cabling” available | January 2010 | |A3.3 |National BPD “Requirements for cabling” finished | Mart-April 2010 | |A3.4 |The initial draft of document “Requirements for data centers and network rooms” available | May 2010 | |A3.5 |National BPD “Requirements for data centers and network rooms” finished| Jun-Septembar 2010 | |A3.6 |The initial draft of document “Requirements for power supply (incl. UPS and generators)” available | Octobar 2010 | |A3.7 |National BPD “Requirements for power supply (incl. UPS and generators)” finished | December 2010 | |A3.8 |The initial draft of document “Requirements for ventilation and cooling” available | January 2011 | |A3.9 |National BPD “Requirements for ventilation and cooling” finished |February-March 2011 |