Plan aktivnosti u grupi za Fizičku infrastrukturu. Plan je predložen i usvojen u subtask-u A3 task-a NA3/T4.
Code | Milestones | Date |
---|---|---|
A3.1 | Working group in subtask A3 established with leader | October 2009 |
A3.2 | The initial draft of document “Requirements for cabling” available | January 2010 |
A3.3 | National BPD “Requirements for cabling” finished | Mart-April 2010 |
A3.4 | The initial draft of document “Requirements for data centers and network rooms” available | May 2010 |
A3.5 | National BPD “Requirements for data centers and network rooms” finished | Jun-Septembar 2010 |
A3.6 | The initial draft of document “Requirements for power supply (incl. UPS and generators)” available | Octobar 2010 |
A3.7 | National BPD “Requirements for power supply (incl. UPS and generators)” finished | December 2010 |
A3.8 | The initial draft of document “Requirements for ventilation and cooling” available | January 2011 |
A3.9 | National BPD “Requirements for ventilation and cooling” finished | February-March 2011 |